within 25 miles, linked to 11 organizations.
- 1Prime Data Center (Dallas)7.9 mi northwest
2 construction registrations, $69.5M · ~4 MW estimated
Low evidence - 2
Registered as a Qualifying Large Data Center Project (Feb 21, 2025)
Low evidence - 3AREP Powerhouse Las Colinas (Irving)12 mi northwest
1 construction registration, $47M · ~3 MW estimated
Low evidence - 4
- 5
- 6
- 7QTS Irving DC3 Data Center14 mi northwest
Registered as a Qualifying Data Center (Feb 9, 2024)
Low evidence - 8State Farm Richardson Data Center14 mi north
Registered as a Qualifying Data Center (Jun 1, 2015)
Low evidence - 9NTT Global Data Centers Americas - Dallas TX414 mi northeast
Registered as a Qualifying Data Center (Apr 18, 2024)
Low evidence - 10LinkedIn Richardson Texas Data Center15 mi north
Registered as a Qualifying Data Center (Feb 20, 2014) · 1 construction registration, $303,000 · ~0 MW estimated
Low evidence - 11QTS Irving 115 mi northwest
Registered as a Qualifying Large Data Center Project (Feb 9, 2024) · 1 construction registration, $152M · ~9 MW estimated
Low evidence - 12Red Oak Texas Data Center 216 mi south
Registered as a Qualifying Large Data Center Project (Mar 14, 2024) · 1 construction registration, $5M · ~0 MW estimated
Low evidence - 13
- 14
- 15Red Oak Texas Data Center17 mi south
Registered as a Qualifying Large Data Center Project (Feb 14, 2022)
Low evidence - 16
- 17
- 18Stream DFW VII Data Center17 mi northeast
Registered as a Qualifying Data Center (Feb 7, 2022) · 2 construction registrations, $20M · ~1 MW estimated
Likely - 19NTT Global Data Centers Americas - Dallas TX317 mi northeast
Registered as a Qualifying Data Center (Oct 1, 2022) · 2 construction registrations, $135M · ~8 MW estimated
Likely - 20NTT Global Data Centers Americas - Dallas TX217 mi northeast
Registered as a Qualifying Data Center (Oct 20, 2022) · 2 construction registrations, $135M · ~8 MW estimated
Likely - 21Independence Data Center18 mi north
Registered as a Qualifying Data Center (Aug 20, 2024)
Low evidence - 22Lincoln Rackhouse18 mi north
Registered as a Qualifying Large Data Center Project (Mar 21, 2023)
Low evidence - 23DFW-04 Data Center21 mi north
Registered as a Qualifying Large Data Center Project (Jan 27, 2026)
Low evidence - 24
- 25Alamo Data Center24 mi southwest
Registered as a Qualifying Large Data Center Project (Nov 2, 2022)